🏔 PLANNING AN OPEN-PIT GOLD MINE WITH A DTM
Hello everyone! 👋
Here's a look at one of our surveys on a gold mining site. The flights were done in the autumn and we're only publishing now, but the project has lost none of its value as a case study: the site gave us around 750 m of vertical relief and ridge lines running off into the distance. The weather, thankfully, was on our side — clear skies and moderate wind, and in terrain like that it's a gift you make the most of quickly.
Which is exactly what we did: in a single day we surveyed an area of more than 1,400 hectares and produced a high-accuracy digital terrain model — the basis for designing the future open-pit gold mine.
👌 Project highlights:
1️⃣ Equipment — DJI Mavic 3E + PPK base station.
2️⃣ Flight parameters — 300 m altitude, 80/60% overlap, 10 m/s ground speed.
3️⃣ Software — UgCS (mission planning), TOPODRONE Post Processing (PPK), Agisoft Metashape (photogrammetry).
4️⃣ Fieldwork — 9 flights, 3 hours, 1 working day.
5️⃣ Deliverables — orthophoto mosaic and digital terrain model (2 m contour interval).
🌐 Accuracy: 6–10 cm on check points (12 ground targets established across the site).
⚙️ How the model is used:
➖ designing pit outlines and waste dumps,
➖ calculating overburden and ore volumes,
➖ siting infrastructure,
➖ modelling drainage systems,
➖ monitoring terrain change over time.
🔖The takeaway: UAV + PPK + dedicated software delivers engineering-grade data in a single day, fully meeting the requirements for 1:2000 scale topographic survey.