11/07/2025
The Horneman Enterprises crew has taken Harrisburg, Lincoln & Lancaster Railroad No. 331 (Formerly known as No. 63 "Leviathan") from completely torn down to the boiler, to operational in 5 weeks. The 1472 Day Federally Mandated Inspection was completed over the course of 10 months, a huge accomplishment.
On top of the 1472 Day Inspection requirements, we reengineered, made, and installed all new driving boxes and bearings, engineered and installed new spring rigging and springs, fabricated a new blast nozzle and delivery pipes, performed a total rebuild of the locomotive's air compressor, calculated a new Form 4 in-house, modified the locomotive's lubrication systems, turned the wheel hubs to improve lateral motion, and resurfaced all journals.